Karuma power plant goes live after 11 years

September 28, 2024

4 minutes read

Karuma power plant

After 11 long years of construction, Uganda’s flagship hydropower project, the Karuma Dam, was finally completed and officially commissioned on Thursday. This marks the end of a complex and challenging journey, filled with technical issues, disputes between the government and the contractor, and other unexpected obstacles.

The project began back in December 2013, when construction of the tunnel-designed power station, an interconnection station, and high-voltage transmission lines was launched. The entire project cost $1.688 billion, with $1.435 billion coming from a loan provided by the China Exim Bank. The remaining amount was funded by Uganda’s government through its energy fund.

Now, the Karuma Dam can generate up to 600MW at peak capacity, bringing Uganda’s total installed capacity to just over 2,000MW—an impressive increase from the 380MW the country had back in 2005. This electricity is produced from a mix of hydro, solar, and thermal energy sources, with hydroelectric power being the main contributor.

During the commissioning ceremony, President Yoweri Museveni highlighted the importance of affordable and reliable electricity for building a modern economy. He recalled a time in the 1990s when a Norwegian independent power producer proposed building a 200MW dam at Karuma Falls, insisting that it was the highest capacity possible. However, President Museveni was not convinced and sought a better solution. When the Chinese entered the picture, they proposed a tunnel design that would increase the power generated using the same water flow, and they also agreed to co-fund the project.

Despite celebrating this major milestone in Uganda’s energy sector, there are still some issues that need to be addressed. At least 21 families displaced by the power dam, which spans 4.6 square kilometers, have yet to be resettled. Energy Minister Ruth Nankabirwa noted that while the resettlement process has achieved 95 percent completion, some families are still pursuing civil lawsuits.

President Museveni offered to provide housing materials for the displaced families, but concerns were raised about the environmental impact of the proposed resettlement area, which is close to a national park and home to elephants. One displaced woman voiced her fear that the area might lead to human-wildlife conflicts.

The construction of the Karuma Dam faced significant challenges from the start. Initially expected to be completed within 60 months, the project ran into technical difficulties early on. Cracks were discovered in the spillway concrete works, leading the Chinese contractor, Sinohydro Corporation, to halt construction for several weeks.

In May 2016, experts from Sinohydro acknowledged the defects and agreed to fix the cracks, assuring that they would not affect the dam’s overall functionality. Similar issues arose with the Isimba hydropower plant, a 183MW project upstream of Karuma, prompting President Museveni to establish a project steering committee to oversee the contractors and ensure that the dams were completed on time.

The COVID-19 pandemic further delayed construction as global travel restrictions prevented engineers from China from flying in. Even after these restrictions were lifted in October 2021, more delays followed due to non-conformities in the electrical-mechanical systems, leading to disputes between the Ugandan government and Sinohydro.

At the dam’s commissioning, officials focused on the achievements rather than the technical difficulties that had plagued the project over its 11-year construction period. Dr. Badru Kiggundu, the former chairman of the project steering committee, mentioned the challenge of vandalism, which at one point caused five towers to fall in a single night, further delaying the project.

With Karuma now operational, Uganda’s Energy Permanent Secretary, Irene Batebe, emphasized that the work is far from over. The country is exploring additional energy sources, including geothermal and nuclear energy, with a goal of reaching an installed capacity of 52,481MW by 2040.

Uganda has ambitious plans to generate 24,000MW from nuclear energy alone, which would make up nearly half of the country’s total energy mix. Last year, the Ugandan government signed a memorandum of understanding with Korea Hydro and Nuclear Power Company Ltd to build the country’s first nuclear facility, a 2,000MW plant in Buyende, eastern Uganda, at an estimated cost of $9 billion.

The government’s energy strategy also includes plans to construct the 840MW Ayago power station in northern Uganda, further boosting the country’s energy capacity and supporting its long-term economic development goals.

Share:
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Related Links

COMESA

COMESA Digital Payments: Platform Transforms Trade in 2025

On October 10, 2025, the Common Market for Eastern and Southern Africa (COMESA) and Zamtel ...

Catholic Church

Kenya Altar Wine: Catholic Church Unveils New Sacramental Drink

On October 4, 2025, the Kenyan Catholic Church introduced a new Kenya altar wine for ...

WHO

WHO Urges India to Strengthen Drug Safety After Child Deaths

The World Health Organization (WHO) has raised serious concerns about weaknesses in India’s pharmaceutical regulations. ...

Peru

Peru Impeaches President Boluarte Amid Unrest

On October 10, 2025, Peru’s Congress removed President Dina Boluarte from office. A late-night session ...

Features

Countries Aircraft

African Countries with the Largest Military Aircraft Fleets in 2025

Africa’s military aircraft fleets are key for defense, surveillance, and peacekeeping. In 2025, several nations ...

Countries

Top 10 African Countries with Best Salaries in 2025

Africa’s job market is growing fast. In 2025, some countries offer great pay. This list ...

Kanye West

New Documentary Explores Kanye West’s Turbulent Journey

A new documentary, In Whose Name?, directed by Nico Ballesteros, offers an intimate look at ...

japa

Top 9 African Countries Sending Immigrants to the United States

Africa’s influence in the United States continues to expand through immigration. Many individuals from the ...

GOLD_3_6

Top 10 Countries Benefiting from Gold Trading in 2025

Gold trading drives wealth for nations with large reserves. In 2025, countries with significant gold ...

FNB-Stadium

Top 10 Most Expensive Stadiums in Africa for 2025

Africa’s sports infrastructure shines with world-class stadiums built for football, rugby, and major events. These ...

Gold

Top Gold-Producing Countries in Africa for 2025

Africa remains a global leader in gold production, contributing significantly to the world’s supply. In ...

digital-nomad-visa

Top 10 Digital Nomad Visa Countries for 2025

As remote work continues to thrive, digital nomad visas offer professionals the chance to live ...

Latest News

Today in History

Error: cURL error 28: Connection timed out after 5001 milliseconds

Exchange Rate Per Dollar

AM Armenian Dram380.8338
GH Ghana Cedi12.1949
GM Gambian Dalasi72
GN Guinea Franc8,634.38
NG Nigerian Naira₦1,462.69
CF CFA Franc BEAC564.4583
12 Oct · CurrencyRate · USD
CurrencyRate.Today
Check: 12 Oct 2025 03:05 UTC
Latest change: 12 Oct 2025 03:00 UTC
API: CurrencyRate
Disclaimers. This plugin or website cannot guarantee the accuracy of the exchange rates displayed. You should confirm current rates before making any transactions that could be affected by changes in the exchange rates.
You can install this WP plugin on your website from the WordPress official website: Exchange Rates🚀

YOUR THOUGHTS

Let us know what you think

Contact the People’s Paper with feedback on stories and how we could make wapress.africa even better!

newsletter image

Stay up to date with the latest from West Africa Press

Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on WApress.

Subscribe Newsletter!

Be the first to receive our latest contents and more...

Need help?